Survitec.

Survitec.

  • Size: 3,000 sq ft.
  • Location: North London
  • Type of Project: CAT B
  • Sector: Professional Services
  • Submarket: Islington
  • Landlord / Tenant: Tenant

Programme

Dthree were appointed 16 weeks prior to their target occupation date.
8 weeks of design development.
4 weeks of furniture procurement.
4 week construction period.

 

The Brief

  • A workplace that has impact and reflects the company’s global presence
  • A combination of independent offices and open plan desking
  • An office design that maximised the natural light of the office floor
  • Office furniture that was high quality and unique to the company’s needs